Table of contents

9. REPORTING AT RBD/SUB-UNIT LEVEL FOR RBMP (SCHEMA RBMPPOM)

The River Basin Management Plan (RBMP) is the main tool for the water management of all surface and groundwater bodies within a specified RBD and the contents of the RBMP are outlined in WFD Annex VII. With respect to water governance, the RBMP shall contain: a general description of the RBD; a summary of the significant pressures and impacts on surface and groundwater bodies; a summary of the measures intended to mitigate the impacts identified; a register of any more detailed plans proposed for sub-basins, sectors, management issues or water categories; a summary of public consultation; and, a list of the Competent Authorities including their relationship with other authorities co-ordinated within a Member State, and a summary of institutional relationships established to ensure co-ordination in international RBDs.

Importantly, the WFD sets Environmental Objectives for Member States to attain for surface and groundwater bodies, the default being ‘good status’ by 2015 (unless an exemption applies or the surface water body meets the conditions for an Artificial or Heavily Modified Water Body). The RBMP is the key tool by which the process to achieve such legally binding Environmental Objectives can be formally set out as a roadmap to implementation and be subject to review.

The WFD sets out a stepwise approach for the development of the RBMP, and if one requirement is not complete or correctly carried out, it may pose obstacles for subsequent steps in the implementation process.

A clear and complete RBMP is also important for accountability as it is also the main tool for communicating to interested parties, including the public, how integrated water management is, or will be, carried out. Complete draft RBMPs including, as appropriate, draft background documents, should be made available in a timely manner through the public consultation process, in order to ensure that interested parties are given sufficient information to enable them to express their views in a meaningful way.

  • EUROMETAUX (invited by kristpet (disabled)) 22 Mar 2019 16:00:37

    We suggest the following revision of the paragraph on "The riverine load approach" end of page 11 (under 9.3.1 Introduction):

    The riverine load approach is limited by the analytical resolution, and in the case of heavy metals also: a) by the fact that only the dissolved fraction (not the solid phase fraction) may have been quantified (in which case the metal fraction bound to suspended matter is not taken into account); and b) by the presence of the natural background metal concentrations, that can constitute a significant part of the total metal load of a water body; quantification of the natural background load of the water body is consequently necessary. The riverine load approach is considered capable of yielding a rough estimation of total diffuse inputs from a catchment if the factors mentioned above are properly accounted for and the point source inputs are known properly quantified.


submit comment

Class RBMP

  1. Please include here any comments which apply to all the schema elements in this Class.
  2. In addition to those general schema element level comments, we welcome your views on: a) whether you think this Class can be simplified;  and b) whether you think the linkages with other reporting Classes or Schemas can be improved, and how;

submit comment

rbmpName - Required.

Name of the RBMP in English.

  • LU - Luxembourg1 (invited by kristpet (disabled)) 26 Apr 2019 14:55:29

    We suggest to report the original name of the RBMP otherwise one will for example not be able to find the document online. An English translation of the name of the document could be added.

  • NO - Norway (invited by kristpet (disabled)) 03 May 2019 10:41:28

    Norway supports LU

submit comment

rbmpTimetablePublicationDate - Required.

Date of publication of the timetable for the production of the RBMP, in the format YYYY-MM-DD.

submit comment

rbmpProgrammePublicationDate - Required.(rbmpProgrammePublicationDate)

Date of publication of the work programme for the production of the RBMP, in the format YYYY-MM-DD.

submit comment

rbmpConsultationPublicationDate - Required.

Date of publication of the consultation measures for the production of the RBMP, in the format YYYY-MM-DD.

submit comment

rbmpInterimOverviewDate - Required.

Date of publication of the interim overview of the Significant Water Management Issues, in the format YYYY-MM-DD.

submit comment

rbmpDraftVersionDate - Required.

Date of publication of the draft versions of the RBMP, in the format YYYY-MM-DD.

submit comment

finalRBMPPublicationDate - Required.

Date of publication of the final RBMP, in the format YYYY-MM-DD.

submit comment

subPlans - Required.(YesNoCode_Enum)

Indicate whether there are specific sub-plans as mentioned in Article 13.5 of the WFD.

submit comment

subPlansCoverage - Conditional.(SubPlansCoverage_Enum)

If there are specific sub-plans, select the issues they address from the enumeration list. If ‘Other’ is selected, specify the issue(s) addressed in subPlansCoverageOther.

submit comment

subPlansCoverageOther - Conditional.

If ‘Other’ is selected from the enumeration list under subPlansCoverage, list the issue(s) addressed.

submit comment

subPlansReference - Conditional.(ReferenceType)

Provide references or hyperlinks to the documents and sections where relevant information relating to the sub-plans can be found. Links to the sub-plans themselves can be provided.

submit comment

sea - Required.(YesNoCode_Enum)

Indicate whether Strategic Environmental Assessments (SEA) have been undertaken on the RBMP and PoM. 

submit comment

seaReference - Conditional.(ReferenceType)

Provide references or hyperlinks to the SEA documents. 

submit comment

publicConsultationInformation - Required.(PublicConsultationInformation_Enum)

Select the mechanism(s) used for informing the public and interested parties about the consultations on the draft RBMP from the enumeration list. More than one mechanism may be selected. If ‘Other’ is selected, specify the tool(s) used in publicConsultationInformationOther.

  • LU - Luxembourg1 (invited by kristpet (disabled)) 26 Apr 2019 15:00:44

    It is not clear for us why does this information has to be reported therefore we would suggest to delete this schema element.

  • NO - Norway (invited by kristpet (disabled)) 03 May 2019 10:43:44

    This should be kept as it is

submit comment

publicConsultationInformationOther - Conditional.

If ‘Other’ is selected from the enumeration list under publicConsultationInformation, list the mechanism(s) used.

  • LU - Luxembourg1 (invited by kristpet (disabled)) 26 Apr 2019 15:01:07

    It is not clear for us why does this information has to be reported therefore we would suggest to delete this schema element.

  • NO - Norway (invited by kristpet (disabled)) 03 May 2019 10:48:26

    Keep as it is.

submit comment

rbmpConsultation - Required.(RBMPConsultation_Enum)

Select the tool(s) used to carry out the public consultation on the draft RBMP from the enumeration list. More than one tool may be selected. If ‘Other’ is selected, specify the tool(s) used in rbmpConsultationOther.

  • LU - Luxembourg1 (invited by kristpet (disabled)) 26 Apr 2019 15:01:18

    It is not clear for us why does this information has to be reported therefore we would suggest to delete this schema element.

  • NO - Norway (invited by kristpet (disabled)) 03 May 2019 10:48:35

    Keep as it is.

submit comment

rbmpConsultationOther - Conditional.

If ‘Other’ is selected from the enumeration list under rbmpConsultation, list the tool(s) used.

  • LU - Luxembourg1 (invited by kristpet (disabled)) 26 Apr 2019 15:01:27

    It is not clear for us why does this information has to be reported therefore we would suggest to delete this schema element.

  • NO - Norway (invited by kristpet (disabled)) 03 May 2019 10:48:43

    Keep as it is.

submit comment

documentProvision - Required.(DocumentProvision_Enum)

Select the method(s) used to provide the public and interested parties with the consultation documents (e.g. draft RBMPs and background documents) from the enumeration list. More than one method may be selected. If ‘Other’ is selected, specify the method(s) used in documentProvisionOther.

  • LU - Luxembourg1 (invited by kristpet (disabled)) 26 Apr 2019 15:01:37

    It is not clear for us why does this information has to be reported therefore we would suggest to delete this schema element.

  • NO - Norway (invited by kristpet (disabled)) 03 May 2019 10:48:53

    Keep as it is.

submit comment

documentProvisionOther - Conditional.

If ‘Other’ is selected from the enumeration list under documentProvision, list the method(s) used.

  • LU - Luxembourg1 (invited by kristpet (disabled)) 26 Apr 2019 15:01:53

    It is not clear for us why does this information has to be reported therefore we would suggest to delete this schema element.

  • NO - Norway (invited by kristpet (disabled)) 03 May 2019 10:49:01

    Keep as it is.

submit comment

documentAvailability - Required.(YesNoCode_Enum)

Indicate whether the consultation documents (e.g. draft RBMPs and background documents) were made available for 6 months for feedback.

submit comment

ongoingStakeholderInvolvement - Required.(OngoingStakeholderInvolvement_Enum)

Select the tools(s) used to achieve the continued active participation of stakeholders in the implementation of the WFD from the enumeration list. More than one tool may be selected. If ‘Other outreach activities’ is selected, specify the outreach activities(s) used in ongoingStakeholderInvolvementOtherOutreach. If ‘Other’ is selected, specify the method(s) used in ongoingStakeholderInvolvementOther.

submit comment

ongoingStakeholderInvolvementOtherOutreach - Conditional.

If ‘Other outreach activities’ is selected from the enumeration list under ongoingStakeholderInvolvement, list the outreach activities(s) used.

submit comment

ongoingStakeholderInvolvementOther - Conditional.

If ‘Other’ is selected from the enumeration list under ongoingStakeholderInvolvement, list the tool(s) used

submit comment

stakeholderGroups - Required.(StakeholderGroups_Enum)

Select the stakeholder groups that have been actively involved in the development of the RBMPs from the enumeration list. More than one stakeholder group may be selected. If ‘Other’ is selected, specify the stakeholder group(s) in stakeholderGroupsOther.

submit comment

stakeholderGroupsOther - Conditional

check: Report if stakeholderGroups is ‘Other’.

submit comment

impactPublicParticipation - Required.(ImpactPublicParticipation_Enum)

Select the impact(s) of the public participation process on the RBMPs from the enumeration list. This refers to the whole RBMP process, not just the 6 month consultation on the draft plan. More than one impact may be selected. If ‘Other’ is selected, specify the impact(s) in impactPublicParticipationOther.

submit comment

impactPublicParticipationOther - Conditional.

If ‘Other’ is selected from the enumeration list under impactPublicParticipation, list the impact(s).

submit comment

internationalCoOrdination - Conditional.(InternationalCoOrdination_Enum)

If the RBD is international, select the type of international co-operation or co-ordination mechanism(s) that exist between neighbouring Member States from the enumeration list. 

submit comment

internationalCoOrdinationPublicParticipation - Conditional.(YesNoCode_Enum)

If the RBD is international, indicate whether there has been international co-ordination on public participation and the active involvement of interested parties.

submit comment

publicParticipationReference - Required.(ReferenceType)

Provide references or hyperlinks to the documents and sections where relevant information relating to public participation and its effectiveness can be found including information on international coordination if any.  

submit comment

consultationResponsesReference - Required.(ReferenceType)

Provide references or hyperlinks to the documents and sections where relevant information on the RBMP public consultation responses can be found.  

submit comment

integrationFloodsDirective - Required.(YesNoCode_Enum)

Indicate whether RBMPs and Floods Directive Flood Risk Management Plans have been integrated into a single plan. 

submit comment

coOrdinationFloodsDirective - Required.(YesNoCode_Enum)

Indicate whether joint consultation was carried out on the RBMPs and Flood Risk Management Plans. 

submit comment

fdCoordinationReference - Required.(ReferenceType)

Provide references or hyperlinks to the documents and sections where relevant information on the coordination of the RBMP with the Floods Directive implementation can be found.  

submit comment

coOrdinationMSFD - Required.(YesNoCode_Enum)

Indicate whether joint consultation was carried out on the RBMPs and Marine Strategy. 

  • LU - Luxembourg1 (invited by kristpet (disabled)) 26 Apr 2019 15:08:04

    We suggest to add the option "Landlocked country".

submit comment

msfdCoordinationReference - Required.(ReferenceType)

Provide references or hyperlinks to the documents and sections where relevant information on the coordination of the RBMP with the Marine Strategy Framework Directive implementation can be found.  

submit comment

Class InputInventory

  1. Please include here any comments which apply to all the schema elements in this Class.
  2. In addition to those general schema element level comments, we welcome your views on: a) whether you think this Class can be simplified;  and b) whether you think the linkages with other reporting Classes or Schemas can be improved, and how;

submit comment

euSubUnitCode - Conditional.

If applicable, report the unique EU code of the Sub-unit. If there are no sub-units this element does not need to be reported and the reporting of the information is done at RBD level.

submit comment

inputInventoryReference - Required.(ReferenceType)

Provide references or hyperlinks to the documents and sections where any other relevant information relating to the estimation of the inputs of pollutants can be found.  Guidance on what should be included in this document is provided in Section 9.3.3.3. 

submit comment

Class InputPollutant

  1. Please include here any comments which apply to all the schema elements in this Class.
  2. In addition to those general schema element level comments, we welcome your views on: a) whether you think this Class can be simplified;  and b) whether you think the linkages with other reporting Classes or Schemas can be improved, and how;

submit comment

chemicalSubstance - Required. (ChemicalSubstances_Union_Enum)

Select each EQSD Annex I substance in turn to provide the information detailed in the following schema elements.

  • SK - Slovakia (invited by kristpet (disabled)) 22 Mar 2019 17:34:30

    Inventory of emissions discharged into surface waters has been carried out and is reported according to the data available from industrial producers who monitor the parameters and provide the measured concentrations into unified register in such indicators as they are stated in the wastewater discharge permissions. Therefore it is not possible for emissions from major polluters to be expressed in a unified set of indicators.

    We propose to establish the possibility to report e.g. total PAH and also single substances for emissions from major polluters.

  • HU - Hungary (invited by kristpet (disabled)) 25 Mar 2019 13:36:22

    „Annex 8e: List of chemical substances (ChemicalSubstances_Union_Enum): Built merging List of pollutants and indicators of pollution in groundwater (AdditionalPollutant_Enum, Annex 8c), Priority Substances (PS_Enum, Annex 8d) and River Basin Specific Pollutants (RBSP_Enum: Annex 8b)”
    We propose to use only one list in which different categories (RBPS, PS etc.) for one substance are indicated.

submit comment

chemicalSubstanceOther - Conditional.

Conditional if ‘chemicalSubstance’ is ‘EEA_00-00-0 Other chemical parameter’ please indicate in this field the CAS number (if relevant) and the name of the pollutant or indicator.

submit comment

inventory - Required.(YesNoCode_Enum)

Indicate if an inventory of emissions, discharges and losses has been completed for this substance. 

submit comment

reportedUnderSoEEmissions - Conditional.(YesNoCode_Enum)

Has the two-step approach in CIS-Guidance No 28 been followed? Step 1 requires an assessment of the current relevance of the substance at the RBD level. Step 2 requires a more detailed analysis for the substances which pass the relevance criteria given in Step 1 (i.e. they are relevant at the RBD level). For those substances that are of minor relevance at the RBD scale (i.e. do not meet Step 1 criteria), MS should try to provide a basic estimation of emissions, discharges and losses from point and diffuse sources: this is particularly important for Priority Hazardous Substances. Together with Schema element relevanceRBDScale this element determines the data-set to be reported for each substance.

  • LU - Luxembourg1 (invited by kristpet (disabled)) 26 Apr 2019 15:11:39

    It is not clear for us why does this information has to be reported therefore we would suggest to delete this schema element.

submit comment

twoStepApproach - Conditional.(YesNoCode_Enum)

Has the two-step approach in CIS-Guidance No 28 been followed? Step 1 requires an assessment of the current relevance of the substance at the RBD level. Step 2 requires a more detailed analysis for the substances which pass the relevance criteria given in Step 1 (i.e. they are relevant at the RBD level). For those substances that are of minor relevance at the RBD scale (i.e. do not meet Step 1 criteria), MS should try to provide a basic estimation of emissions, discharges and losses from point and diffuse sources: this is particularly important for Priority Hazardous Substances. Together with Schema element relevanceRBDScale this element determines the data-set to be reported for each substance.

submit comment

relevanceRBDScale - Conditional.(YesNoNotApplicable _Enum)

To be answered for reported substances. "Yes" if proceeding to second step of two-step approach. (See criteria on pages 9-10 of the CIS-Guidance No 28.) "No" leads to optional point source assessment. Any knowledge of quantifiable inputs of priority hazardous substances should be reported. “Not applicable” if the Two Step Approach has not been used.

submit comment

inventoryMethodology - Required (InventoryMethodology_Enum)

Required for all substances reported. Indicates the approach used to determine the reported inputValue (and inputCategoryValue if reported). Further descriptions of Tiers 1-4 in CIS Guidance Document 28. Other methodology to be detailed (see inputMethodReference). May be different for different substances and individual input categories. Tier 1 automatic if "No" re "relevanceRBDScale".

  • RO - Romania1 (invited by kristpet (disabled)) 18 Mar 2019 08:28:03

    It should be reported only for those substances/pollutans that pass the relevance criteria, if "relevance RBD Scale" is "Yes". For others it should be optional. Conditional check: report if relevanceRBDScale is "Yes".

submit comment

inputDataQuality - Optional.(InputDataQuality_Enum)

It can be reported if quantitative data for this substance is reported. To reflect the reliability and variance of the data provided, taking into account issues such as the availability of monitoring data, the reliability of emission factors used in calculations, the difficulty of taking account of seasonal influences in areas with high seasonal variation etc. E.g. very good would imply a substantial monitoring basis, very uncertain would imply a very weak or absent monitoring basis (heavy reliance on estimation).

submit comment

inputMethodReference - Conditional.(ReferenceType)

Required if "Other" methodology is specified under inventoryMethodology. Desirable if approaches in CIS-Guidance Document 28 have been elaborated or described in an electronic freely accessible version of the national emission inventory for EQSD Annex I substances, in specific documents as part of RBMP reporting, in international seas convention guidance documents or similar. URL-Reference to specific documents.

submit comment

inputTotalType - Conditional.(InputTotalType_Enum)

Required for all EQSD Annex I substances reported. Optional for other substances/parameters. Distinction between total point and total diffuse expected for EQSD Annex I substances.

  • RO - Romania1 (invited by kristpet (disabled)) 18 Mar 2019 08:43:08

    It should be reported only for those substances/pollutans that pass the relevance criteria, if "relevance RBD Scale" is "Yes". For others it should be optional. For those substances not being relevant isn't possible to report the load. Conditional check: report if relevanceRBDScale is "Yes".

submit comment

inputTotalValue - Conditional.

Required for all EQSD Annex I substances reported. Optional for other substances/parameters. Input = emissions, discharges and losses.

  • RO - Romania1 (invited by kristpet (disabled)) 18 Mar 2019 08:43:57

    It should be reported only for those substances/pollutans that pass the relevance criteria, if "relevance RBD Scale" is "Yes". For others it should be optional. For those substances not being relevant isn't possible to report the load. Conditional check: report if relevanceRBDScale is "Yes".

  • LU - Luxembourg1 (invited by kristpet (disabled)) 26 Apr 2019 15:21:59

    We suggest to add the possibility to provide a short explanation if no input value can be provided (e.g. because of a lack of data).

submit comment

inputTotalUnit - Conditional.(UnitOfMeasure_Enum)

Required if inputTotalValue is reported.

submit comment

inputYearPeriod - Conditional.

4-digit number (should ideally be 2008, 2009 or 2010 as reference year) required for EQSD Annex I substances and for other substances for which an inputValue is reported. Calendar year to which the load applies. A period of up to six years within the relevant RBMP period may be indicated by a start and end year, separated by a double hyphen ( yyyy--yyyy ).

submit comment

inputTrend - Optional. 

For each chemical substance a trend (positive or negative) can be reported directly (self-assessed), independently of any trend that might be calculated directly from the datasets reported for those years.

  • SE - Sweden (invited by kristpet (disabled)) 22 Mar 2019 13:37:36

    What does this mean? A trend in amounts released, or levels found in the environment.

submit comment

inputTrendPeriod - Conditional.

If inputTrend is reported, report first and last years of trend assessment.

submit comment

Class InputCategory

  1. Please include here any comments which apply to all the schema elements in this Class.
  2. In addition to those general schema element level comments, we welcome your views on: a) whether you think this Class can be simplified;  and b) whether you think the linkages with other reporting Classes or Schemas can be improved, and how;
  • BE (invited by kristpet (disabled)) 03 May 2019 17:52:17

    A lot of options, a lot of source categories (P1-P13 or 1.1- 2...)... we think the figures of the different countries are not comparable. ->so, only ask for data when you expect to use it 

submit comment

inputCategoryCode - Required.(InputCategory_Union_Enum)

Allows apportionment of inputs between different sources/pathways. 

submit comment

inputCategoryScheme - Required.(InputCategoryScheme_Enum)

Identifies the type of emmissions apportionement being used.

submit comment

inputCategoryValue - Required.

The multiplicity of the whole Class InputCategory is 0 to many. If the class is reported, this schema element must be included.

  • LU - Luxembourg1 (invited by kristpet (disabled)) 26 Apr 2019 15:25:50

    We suggest to add the possibility to provide a short explanation if no input value can be provided (e.g. because of a lack of data).

submit comment

inputCategoryUnit - Required.(UnitOfMeasure_Enum)

The multiplicity of the whole Class InputCategory is 0 to many. If the class is reported, this schema element must be included.

submit comment

inputUWWTPCoverage - Conditional.(InputUWWTPCoverage_Enum)

If categories for Urban Waste Water Treatment Plants are reported please indicate the coverage. Please note that under WISE SoE specific categories exist for this purpose (U11, U12, U13, U14, U21, U22, U23, U24).

  • BG - Bulgaria (invited by kristpet (disabled)) 27 Mar 2019 17:48:55

    In order to make the reading the guidelines easier, it would be appropriate to be conducted a hyperlink to the pointed Annex - “(see Annex 8n)"

    Please note that this comment is relevant to all texts that are pointing to Annexes.

  • NO - Norway (invited by kristpet (disabled)) 03 May 2019 10:58:10

    Agreed with BG

submit comment

inputIndustryCoverage - Conditional.(InputIndustryCoverage_Enum)

If categories for Industrial Waste Water Treatment plants are reported please indicate the coverage. “E-PRTR” means large facilities with releases to water reported in E-PRTR; “national business registers” means including also medium size facilities with emission data in registers; “all manufacturimg industries” means including also small size facilities with direct discharges based on economic activity extrapolations. 

submit comment

riverineLoadMonitoringSite - Optional.

If reporting inputCategoryValues as riverine loads, provide the code of the monitoring station used as a basis.

submit comment

Guidance on the contents of RBMPs/background documents

(Please see the full text of this sub-section in the WFD Reporting Guidance 2016 or above chapter)

Include here any comments that relate to the information contained in this sub-section of the Reporting Guidance, namely concerning information you think could/should be reported electronically and information which you believe should not be included in the River Basin Management Plans or background documents.

submit comment